1. Installation Process

1.1 Site Requirements

1.1.1 Banned under 10 ℃ temperature condition for installation on site.

1.1.2 All ground floors must be dry, flat, uncracked, constructed, and clean.No dust, paint, paraffin, lubricants, grease, asphalt, old adhesive and other foreign impurities.

1.1.3 The rubber flooring is made of seamless splicing, splicing seam straightening, smooth and solid, with no apparent color difference.

1.1.4 All hardened treatment, hardened water treatment and damaging compounds must be removed mechanically.

1.1.5 The humidity at the bottom floor should be lower than 2.5%, and the lower ground floor, where humidity is above 2.5%, is not recommended.If the occurrence of such humidity is above 2.5 percent, it shall be treated according to industrial standards.

1.1.6 The surface unflatness within 5 millimeters can be flattened by self-leveling.

1.2 Construction Preparation

Rubber floor should be moved to the construction site ahead of schedule, adapt to the temperature is not less than 24 hours, Mr Should be laid first row, direction of arrow back and keep the floor, and then according to the terrain and the design scheme for stitching cut.

1.3 Construction Procedure

1.3.1 Positioning Measurement

Determine the center of each end wall, and connect these points to the center of the room by drawing a chalk line. 

Determine the center of the line and draw a perpendicular line through the carpenter's ruler to connect the two sides of the wall.

1.3.2 The installation of the ground plate

After the room is properly measured, you can measure a convenient and valid starting point with these measurements.

After the first row is laid, the ground plate of the row is adjusted by using a straight edge or a tight rope, making it a straight line.

After the installation is complete, check the amount of paint in the area of the floor.

Note:

A proper trowel must be used to match the appropriate slots to ensure sufficient adhesion.

The pressurized installation of the rubber ground plate will not cause the wrinkling.

1.3.3 The bonding of the earth plate

In order to install and obtain the maximum glue time, place the adhesive as quickly as possible on the installation floor and spread out.

Use the recommended trowel to spread the adhesive and spread it equally over the binder.

Use the 50kg roller to roll down the floor surface, flattening the gap in the adhesive, to make sure that the air is completely removed.

Periodically examine the ground plate to verify that it has good adhesion ability.

1.3.4 The passage

After the ground plate is compressed by the roller, it should be avoided in addition to the necessary installation work. The adhesive should also be restricted.The adhesive should be able to walk slightly in a full 12 hours.Avoid frequent walking in 24 hours.Under normal conditions, the adhesive will be completely frozen for 48 hours.

1.3.5 The final application

Check whether the adhesive is glued to the whole floor.

The passage is prohibited within 12 hours.

In 24 hours, it is forbidden to walk frequently.

The passage of heavy equipment or vehicles is prohibited within 72 hours.

The protection of the ground during installation and installation will not be affected by daylight, moisture, and other construction work by covering a 1-2 day period.

During the period of cement solidification, should maintain recommended temperature (15 ~ 30 ℃).

In 72 hours, avoid touching the finished floor of the original clean, so that the adhesive is completely solidified.

Note: when the adhesive is not entirely solidification or original dope is too thin to connect to plate thoroughly, it will be a slightly tilted at the edges.In this case, a sandbag or weight should be used to press the edge of the warped line until the glue is completely set and is sufficiently cohesive.

2. Clean

2.1 In clean water, add 1 cup of fabric cleaner per half bucket of water to make the rubber floor look like a new waxing.

2.2 The use of multifunctional detergent solution is good for cleaning rubber floors.We first need to read carefully the precautionary measures on the product label, and then test it in the floor corner.

2.3 Remove the footprints of rubber floor can dip in with liquid wax of high steel wool, to gently wipe besmirch wipe out process, reoccupy wet cloth to wipe dry.

2.4 Use a cleaner or dewaxing agent to remove the accumulated wax.

2.5 Solvent products may soften and destroy rubber floors.

2.6 Don't wash the floor with water, too much water will make the glue of the floor to fall off.

Related Industry Knowledge

Related Products

  • Wholesale Gym Flooring Rubber Rolls Heavy Duty Gym Flooring Suppliers Ideal Rolls Wholesale EPDM Rubber Rolls Weight Lifting Rubber Flooring For Sale
  • World's Newest Electronic LED Fitness Gym Equipment Ideal Mats Digital Fitness Coach Suppliers Digital Fitness Coach Wholesale Gym Management System For Sale
  • Newest Self Adhesive Acoustic Floor Underlayment Wholesale Ideal Easy Soundproofing Rubber Underlay Wholesale  For Carpet Floor Tiles Installation
  • Childrens Rubber Floor Tiles Ideal Tiles Stable Outdoor Playground Safety Rubber Play Tiles for Kids Playground EPDM Rubber Flooring For Sale Wholesale EPDM Playground Surface
  • EPDM Rubber Running Track Accessories For Sale Durable Outdoor and Indoor Running Track Material For Synthetic Run Tracker
  • Rubber Floor Underlayment Wholesale Ideal Rolls Non Slip Material Basement Rubber Floor Underlay for Basement Over Concrete